CALIFORNIA'S PEX-ISO: RACING TO COMPLETION

Transmission & Distribution World January 1998

By Chuck Newton, Automation Editor



Far-reaching changes are taking place around the world in the way that utilities control and manage their electric systems. The onset of active market competition and deregulated electricity markets have mandated development of new market structures, such as independent system operators (ISO).

Early last year the state of California awarded an ISO system contract to the System Control segment of ABB Information Systems, a division of ABB Power T&D Company, Inc. The initial development effort was for a power management system (PMS) similar to the traditional energy management system (EMS) that utilities have used for years. The big difference between a traditional EMS and the California's ISO's system is that the PMS will manage the transmission assets of all utilities in the state of California—a new concept that will forever change the operations of the utility industry.

ABB and its alliance partners, Perot Systems and Ernst & Young, were then awarded a subsequent contract to develop a Web-based Scheduling System and a Balance of Business System to compete the package.

The Scheduling System has two main sub-systems:

  • Scheduling Infrastructure-to manage contract bidding and scheduling activities.
  • Scheduling Applications-to handle ancillary services, congestion management and pricing , balancing market and ex-posting pricing, assessment of transmission capacity, and routing activities.

The Balance of Business System covers settlements, billings, credits and system administration modules.

The California ISO system development and integration project (actually two separate, but related, project awards) is especially notable for three reasons:

  • Lack of Precedence: The project had no prior model to follow. In fact, this system architecture may well become the model for several other states. Much will depend on the operational effectiveness and "market acceptance" of the technology in the first few weeks of live operation.
  • Short Development Schedule: Incredibly tight scheduling—numbered in months, rather than years—was mandated to ensure availability of the PMS and related scheduling infrastructure, scheduling applications and balance of business systems.
  • Complexity of Linkage with External Systems: Adding to the complexity of the PMS, external linkages had to be implemented with other operating control systems in three large California utilities using multiple standard and proprietary communications protocols (fig. 1). A specially developed, and secure, Web site provides market demand and supply information, and enables collection of power contract bidding and publishing capabilities.

While some formidable obstacles have been in place, including "glass-house" working conditions, significant technical challenges and the complexities of working with multiple organizations, the system was working in test environments within the design criteria originally established.

Based on a personal demonstration of the system, albeit in "lab conditions," my impressions are:

  • The first phase of the ISO system will likely exceed the key design criteria specified for Phase One deliverables. Keep in mind that this project is a multi-phased development effort with phased deliverables running well into the future.
  • The power exchange (PEX) system will work in a technical sense. We have to remember that the California initiative is the "Lewis and Clark expedition" of today's electric utility industry, charting a course into unknown territories. It is understandable to expect that changes have been requested and will continue to be made during the system's initial period of testing and operation.
In closing, remember that a wide range of people and interests are involved in this project. After observing the commitment of the state ISO organization and the multiple companies involved in this project, I believe that once implemented, the California PMS will perform better than some industry observers have predicted.